> Canada
This new from the ground up nuclear power plant has North America’s first turbines ever set on a gerb spring foundation. Everything from condenser and turbine is set on springs to reduce number of pipe locations, adjustable for alignment, absorbs vibrations, and provides seismic advantages.
TurbinePROs provided all skilled craft labor from 90 different crafts, on-site project manager, safety and quality managers, and onsite machining. Unique procedures and work packages, ITPs and JSAs were developed for the installation of 2 - 1,117 MW Toshiba turbines and ancillary components including 6 LPs, 2 HPs, 2 generators, 2 collectors/exciters, all valves, GERB springs, feed water pump overhaul, Lube Oil Flush Support, Testing Support, Startup Support. And all tooling, consumables, as well as all sole plates and fixators required for turbine installation.
In addition, TurbinePROs developed installation procedures and ensured stable operating conditions. Our project manager oversaw all receivables, balance of plant in turbine building including pumps and motors installation, alignment, and maintenance.
TurbinePROs was also chosen to provide continued maintenance support.
OEM: Toshiba
Fuel Type: Nuclear
90 Skilled Crafts
1,117 MW
Number of Units: 2
Unique Challenges:
Everything from the condenser and turbine are set on a GERB spring foundation. This is the first time in North American that a turbine deck and condenser were supported by GERB springs and Viscodamper.
Safety Award: 400,000 Safe Man-Hours
TurbinePROs has always been committed to our customers', employees', and entire project team's health and safety. Now, providing the safest, most productive services to power-generating facilities while minimizing and preventing the spread of COVID-19 is of paramount importance. We have worked diligently to develop solutions and protocol above and beyond the CDC's standard health and safety guidelines to mitigate Coronavirus infection while we are servicing critical plant components vital to infrastructure.
We understand there’s no time for downtime at your plant so TurbinePROs has a fully stocked Rapid Response Service truck ready to mobilize with the tools and supplies needed to get the job done. Our team of field services experts are ready 24/7 to provide emergency repairs, maintenance, new installation, and other services for all types of rotating equipment.